Terjola water project worth over GEL 15.8 million reaches 86% completion
Share
Save
Terjola's water-supply reconstruction is approaching completion, Georgia's Ministry of Infrastructure reported on 18 November. Once the project is finished, up to 5,330 residents are expected to receive uninterrupted water service around the clock.
The contract exceeds GEL 15.8 million. New storage reservoirs with capacities of 300 and 2,000 cubic metres have been built, alongside pumping infrastructure. Contractors have laid 43.6 kilometres of a planned 44.5-kilometre distribution network and installed 74 fire hydrants.
The ministry put certified financial completion at 86%. A remote monitoring and control system, SCADA, is also being installed. Continuous 24-hour service remains the planned outcome on completion, rather than a service already delivered to every household.